Successful first stage at Holly Cross ATFS Energisation
Successful first stage at Holly Cross ATFS Energisation
November 1, 2024
On the weekend of 18th-19th October, Enable Power Systems, alongside our supply chain partners, completed Stage 1 commissioning of a new 25kV auto transformer feeder site (ATFS) at Holly Cross, Bramley.โฃ
This complex task involved collaboration with National Grid teams to energise the new Holly Cross 25kV grid intake substation, fed through the Bramley 400kV substation. Key achievements in this phase included:โฃ
โข ๐๐ง๐๐ซ๐ ๐ข๐ฌ๐ข๐ง๐ ๐๐๐ญ๐ข๐จ๐ง๐๐ฅ ๐๐ซ๐ข๐ & ๐๐๐ญ๐ฐ๐จ๐ซ๐ค ๐๐๐ข๐ฅ ๐๐ง๐๐ซ๐๐ฌ๐ญ๐ซ๐ฎ๐๐ญ๐ฎ๐ซ๐: 400kV to 25kV HV cables, switchgear, protection schemes, ABB SMOS switchgear, and 2 autotransformers. โฃ
โข ๐๐๐๐ฆ๐ฅ๐๐ฌ๐ฌ ๐๐จ๐๐ค ๐๐๐ฌ๐ญ๐ข๐ง๐ : Rigorous testing ensured all equipment met high safety and compliance standards without impacting Network Rail’s operations.โฃ
With Stage 1 completed and the site de-energised, weโre ready to enter Stage 2 with short circuit testing scheduled for early November.โฃ
Thanks to our dedicated teams and partners for executing this crucial milestone on time and to the highest standards.โฃ
Stay tuned for more updates as we continue to drive progress on this pivotal project for UK rail infrastructure!